Kilburn Library Reimagined

This report is to seek approval for an approach to procuring architectural and construction design management (CDM) services to complete the Kilburn Library redesign to completion of the project. The approach is to use the Bloom framework of which Camden are already a member to complete a direct award to the architect that completed Royal Institute of British Architects (RIBA)  Stage 3 designs to support the acquirement of external funding from the Arts Council.

 

The estimated contract value is £154,000 to complete the project up to RIBA Stage 7.

Decision type: Non-key

Decision status: Recommendations Approved

Wards affected: Kilburn;

Notice of proposed decision first published: 06/02/2025

Decision due: 29 Jan 2025 by Director of Recreation

Department: Supporting Communities

Contact: Fiona Tarn, Head of Libraries Email: Fiona.Tarn@camden.gov.uk Tel: 020 7974 4001.