Decision Maker: Cabinet
Decision status: For Determination
Is Key decision?: Yes
Is subject to call in?: Yes
To approve a procurement strategy for a Capital Works framework and to
delegate approval of the award of the contracts to the Executive Director Supporting Communities in consultation with the Cabinet Member or Better Homes.
RESOLVED –
(i) THAT the procurement strategy for the construction and property framework and supporting mechanisms be approved, and it be noted that the value of the procurement is approximately £300m over the four-year period and that, to provide maximum flexibility, the contract notice advertising the framework will include a maximum potential value of £500m;
(ii) THAT authority be delegated to the Executive Director Supporting Communities, in consultation with the Cabinet Member for Better Homes, to award the Framework contracts for the Camden Construction and Property Works Framework;
(iii) THAT authority be delegated to the Executive Director Supporting Communities, in consultation with the Cabinet Member for Better Homes to approve the procurement strategy for contracts procured under the proposed Framework (“call-off contracts”) where the value is £5m or more; and
(iv) THAT authority be delegated to the Executive Director Supporting Communities, in consultation with the Cabinet Member for Better Homes to award contracts procured under the proposed Framework (“call-off contracts”) where the value is over £5m but below £10M.
Report author: Susanne Afra
Publication date: 21/12/2023
Date of decision: 20/12/2023
Decided at meeting: 20/12/2023 - Cabinet
Effective from: 03/01/2024
Accompanying Documents: