Decision details

Camden Capital Works Framework Procurement (SC/2023/41)

Decision Maker: Cabinet

Decision status: For Determination

Is Key decision?: Yes

Is subject to call in?: Yes

Purpose:

To approve a procurement strategy for a Capital Works framework and to

delegate approval of the award of the contracts to the Executive Director Supporting Communities in consultation with the Cabinet Member or Better Homes.

Decision:

RESOLVED –

 

(i)            THAT the procurement strategy for the construction and property framework and supporting mechanisms be approved, and it be noted that the value of the procurement is approximately £300m over the four-year period and that, to provide maximum flexibility, the contract notice advertising the framework will include a maximum potential value of £500m;

 

(ii)          THAT authority be delegated to the Executive Director Supporting Communities, in consultation with the Cabinet Member for Better Homes, to award the Framework contracts for the Camden Construction and Property Works Framework;

 

(iii)         THAT authority be delegated to the Executive Director Supporting Communities, in consultation with the Cabinet Member for Better Homes to approve the procurement strategy for contracts procured under the proposed Framework (“call-off contracts”) where the value is £5m or more; and

 

(iv)         THAT authority be delegated to the Executive Director Supporting Communities, in consultation with the Cabinet Member for Better Homes to award contracts procured under the proposed Framework (“call-off contracts”) where the value is over £5m but below £10M.

Report author: Susanne Afra

Publication date: 21/12/2023

Date of decision: 20/12/2023

Decided at meeting: 20/12/2023 - Cabinet

Effective from: 03/01/2024